Thursday, September 1, 2011

Sticking to Estimates

I got a great comment from Kelly Waters on my recent post "Scrum: No commitment required" via his web site. After responding I realized that the response was a good basis for this follow-up to my original post.

In the original version of Scrum, the commitment of the team for the sprint is dependent on two things: a good work ethic and good estimates. If either one is an issue, then the work won't be done on time. The “no commitment required” title of my previous post was a bit tongue in cheek. Absolutely commitment is important, but I don’t think that making it part of “Scrum” will suddenly make team members with a poor work ethic suddenly have a good work ethic or team members with problems estimating better at estimating. Nor will having commitment part of Scrum automatically improve a bad team/PO dynamic. 

People with a good work ethic will work hard. If you have folks with a poor work ethic, I believe Agile will expose this more clearly and then you can use your management skills to address it one way or another. Hopefully, with a win-win solution.

Estimates are just that, estimates. They are a good-faith representation of what the team believes it will take with the information they have at hand. When something is discovered, then it is important for the team to communicate that to the PO, but I don’t think it means that they have to stick to the original estimate. Is that “letting them off the hook?” I don’t think so. Let’s face it, if they estimate 8 hours, but it turns out to take 24, the only way to do it in 8 is to do 8 hours “on the books” and 16 hours off. To have the team absorb those extra 16 hours means that they will have to take it out of their own time which is violating the idea of sustainable pace.

If you have a team that consistently misses their estimates, that’s something different. Missing estimates should be the exception rather than the rule. When it becomes the rule, the question is what’s going on? Is team morale low? Why?

When using story points combined with tracking velocity, there shouldn't be a problem with estimates because story points and velocity should make the issue of estimates a moot point. What I mean is that if all estimates are suddenly off by a factor, the result is simply that velocity goes down. If estimates have always been "off" then velocity will not be going up or down, it will just be fairly constant. Since story points and velocity are relative, estimates that are "off" by a factor aren't a real problem.

Instead, the “problem” may be manifesting itself more as a general feeling of “this team just doesn’t seem to be as productive as it could be.” But then you are back to “why not?” I don’t think an enforced framework of commitment will change anything if the team has, for instance, low morale.

On the other hand, if the problem is wildly varying velocity (perhaps due to wildly varying accuracy of estimating stories) then I would venture there is a good chance that the stories are just too big in general and a good remedy to consider is to aggressively split stories into smaller stories.

Monday, September 28, 2009

Planning Poker Reduces Risk and Waste

There are three particularly valuable things that can happen during a Planning Poker session. They may also happen during any flavor of estimation meeting, but seem to be more likely when using Planning Poker.

The Bigger They Are, The Harder They Fall
I recommend that you never use a story size greater than 13. Most stories that are estimated at 8 points or above can be split into smaller stories. You should always be looking for opportunities to break larger stories into smaller stories. If you have an 8 point or larger user story, it is probably actually two or more stories in disguise. The bigger the story, the more likely your estimates are wrong and the more likely that you have many smaller stories masquerading as one large story.

For instance, you may find that a story that originally looked like a 20 point story was really two 8 point stories, one 5 point story and 2 three point stories for a total of 27 story points. Better to break that huge story down into its five constituent stories and estimate them each individually.

But remember, a story is only a story if it provides value to the user. Splitting a story up into “As a user I want the backend for X” and “As a user I want all of the UI for X” is not the right way to go. If you can’t create smaller stories that still provide user value, then the story is already as small as you currently know how to make it.

Know When to Walk Away
You may realize while discussing a story that the story contains a big unknown, something that feels like it won’t be resolved during the implementation of that story. In that case it is best to split the story up into a research story and the story itself. For instance, “As a developer I want to know how to XYZ.” That way, if you never do figure out how to do the unknown part, you haven’t invested any effort into the overall story. This technique should only be used as a last resort, but it is much better to do this than to know going in that there is a big unknown and have to pull the whole story out near the end of the iteration.

Know When to Fold’em
Lastly, you may decide that you just don’t have enough information to estimate a story. In that case, you should have a mechanism for informing the product owner such as marking the story “need more info.” There’s no point spending time on estimation if there is insufficient information to do so. You’ll just be glossing over the problem and producing a false sense of security.

Breaking out research stories and kicking stories back to the product owner may seem like procrastinating, but it tends to build good habits. It keeps the team from committing to work that includes research projects, clearly defining some stories as research stories, and keeping the product owner on his or her toes.

Counting Your Chips
In summary, if you are mostly working on small user stories that have end user value, you are reducing the chance that you are putting something into the product that never gets used and you are also reducing the chance of starting work on something that never gets finished or has to be discontinued part of the way through. The smaller your stories, the smaller your risk and the less effort you’ve wasted when you run into problems.



See Also: "The Five Essential Ingredients of Great Agile Estimation"

The Five Essential Ingredients of Great Agile Estimation

Planning Poker is a useful Agile estimation technique (see previous post "Introduction to Planning Poker"), but it is even more useful when used in conjunction with whole teams, user stories, velocity, and story points. I refer to these five practices, used together, as the five essential ingredients of great Agile estimation.

Whole Teams
A key practice of Agile development is the use of whole teams. A whole team is a cross-functional team comprised of between 5-9 people. By cross-functional I mean the team as a whole contains all of the skills needed to accomplish the team’s goals, not that each team member is capable of doing any task. If you have more than 9 people, then you split people up into multiple whole teams.

Planning Poker reminds everybody that the estimate includes all of the work that needs to be accomplished in order for the story to be considered done. It includes development, testing, documentation, and anything else required for the story to be considered done. It is a reminder that nobody on the team gets credit for a job well done until the whole story crosses the finish line. Instead of people saying “well, I finished the development, I don’t know what is taking the tester so long” they are more likely to say “what problem are you running into and how can I help?”

User Stories
Because user stories are a simple and easy to understand description of the work, user stories allow you to focus on estimating rather than spending lots of time discussing what a particular enhancement request or requirement really is. To maximize the benefits of Planning Poker, you need to be good at creating and using user stories.

Story Points
In my experience, the best unit to use for estimates is story points. Two different people with two different skill sets or levels of ability in an area may take different amounts of time to perform a particular task. Estimating in hours mixes together the scope of the work that needs to be done with the speed at which a particular individual can do that work.

On the other hand, story points are a relative measure of the scope of a user story. Story points separates out the “what” from the “who.” For instance, if you have one individual that is stronger with .Net than with Java, they will estimate a Java story as taking more hours than somebody that is stronger with Java. But they will probably both agree that something that is twice as easy to implement will take half as long to do.

To use story points, you need to create a relative scale of scope. A simple approach is to find a simple and straightforward story that you use to represent a single story point. Then think of stories that are 2, 3, 5, and 8 times larger in scope. You should have a couple of examples for each story point value to take into account that some stories have more test than coding, more documentation than test, etc.

Story points are primarily used for planning, not for implementation. Story points are used to help determine the contents of an iteration by calculating a velocity.

Velocity
In Agile, the velocity of a team is simply the number of story points associated with stories that are finished in an iteration. For instance, if the team completed 8 stories that were each 5 points in an iteration, then their velocity for that iteration was 40 story points. In a stable team, a team that is comprised of the same individuals working full time as part of that team, the velocity is a good measure of the overall throughput of the team.

Knowing your velocity helps with planning. For example, if you know that the velocity of your team is 40 points, then you know you can expect 40 story points for each iteration. The team decides which stories to take based on the backlog which is maintained by the product owner.

More Than the Sum of The Parts
Regardless of which of these practices you are currently using – whole teams, user stories, story points, velocity – Planning Poker is an excellent tool. The more of these practices you use, the more they reinforce each other and the more value you will get out of Planning Poker. Conversely, the more you use Planning Poker, the more value you will see in implementing all of these practices.



Next: Planning Poker Reduces Risk and Waste

Introduction to Planning Poker

Many of the techniques of Agile development combine together to provide more than the sum of their parts. One technique that definitely fits this description is the Planning Poker method for doing estimation. In part 1 of this post, I will quickly describe the mechanics of Planning Poker. I will then go on to describe how user stories, whole teams, story point estimation, and velocity all work to multiply the value of Planning Poker and how Planning Poker also reinforces the use of and value of the other practices. If you are already familiar with Planning Poker, you may want to skip ahead to "The Five Essential Ingredients of Great Agile Estimation".

Planning Poker is an estimation technique first described by James Grenning in 2002 in a paper by the same name [pdf]. When I first heard about Planning Poker, I couldn’t help but chuckle. It seemed a bit silly to mix software development and poker. After reading Mike Cohn’s excellent book “Agile Estimating and Planning” I had a good grasp of the mechanics of Planning Poker, but it felt like just a variant of the Delphi method and thus nothing new.

About a year ago we had Kenny Rubin come in to do some Scrum training for us. That was just the shot in the arm that we needed to supercharge Agile adoption at AccuRev. If you are looking for an Agile trainer, I highly recommend Kenny Rubin. It was based on Kenny’s explanation and recommendation that we decided to try Planning Poker on a real project. The results were terrific and after a single session we were hooked. Planning Poker is now a standard part of our Agile process.

The Basics
In order to play Planning Poker, each participant will need a deck of Planning Poker cards. These are easy to obtain, just Google for “Planning Poker cards” or make your own. You will need the following cards: ½, 1, 2, 3, 5, 8, 13, 20 and a card that indicates “I’ve had enough.” The numbers on the cards represent estimates. You can use story points, ideal days, or some other measure, but in this point I am assuming (and advocating) story points. Typical decks contain cards for much larger numbers than 20, but I think you’ll find that 20 and higher are rarely used once you’ve been using Planning Poker for a year or two.

The whole team gets together for a set amount of time to do story estimation. An hour is usually a good amount of time, but this is completely up to you. When I say “the whole team” I am assuming that you are using small cross-functional teams of 5-9 people (see later parts that discuss the use of whole teams).

Estimation is done on a story-by-story basis in the same order as the backlog, starting with the first story that needs estimating. Somebody reads and describes the story. This is often the product owner, but could be anybody. Some teams do story point estimation without the product owner and just skip stories which they are unable to do without the product owner’s involvement. After the story has been read, participants discuss the story for a bit and then decide on an estimate by picking one of their cards and laying it face down in front of themselves. Once everybody is ready, all of the estimates are shown. If the estimates are all the same, you are done.

Usually, some of the estimates are particularly low or particularly high. A low estimate can indicate that the estimator left something out, or possibly that they know a way to reuse existing work or have some other good information that other folks weren’t aware of. A high estimate may indicate many things, but most commonly it means that the estimator is thinking of something that other folks may not be aware of. For instance, somebody may point out that there is no test framework or tooling for a particular technology and that to adequately test the story the team will need to do a lot of setup work.

In any case, after a round of discussion, everybody chooses a new estimate. This is repeated until the team comes to consensus on the estimate. The estimate is given to the story and then you move on to the next story. You end when you hit the end of the meeting time, you run out of stories to estimate, or somebody plays the “I’ve had enough” card.

The Benefits
One of the biggest benefits of Planning Poker is the sense of team that it creates. The whole team is participating in the estimation. This creates a greater sense of team ownership and team responsibility for each story. Another major benefit of Planning Poker is that you leverage the collective wisdom of the whole team. However, this really only works well when you are using whole teams in the Agile sense of the term.



Next: The Five Essential Ingredients of Great Agile Estimation

Wednesday, September 23, 2009

Specification is Planning is Design is Coding is Approximation

All Phases of Software Development are Variations on a Theme
It is easy to think of specification, estimation, planning, design, implementation, and customer feedback as completely separate and unrelated activities. However, a useful way to think about them is as variations on a theme where the theme is producing a product which provides the best return on investment as measured by the ratio of revenues to cost. Each of the phases of the development life-cycle can be thought of as a combination of discovery, prediction, and design. The prediction comes into play when you make a decision. When you decide that you will schedule a particular requirement to be implemented in your product, you are predicting that the end result is something that will provide value to the customer. You have no way of being sure until the customer has actually used it as part of their normal course of business.

What does it matter if in fact it is true that all of these activities are variations on a theme? I believe it provides a conceptual framework that can help us make better decisions about the products we create and the way we go about creating them.

Requirements Gathering is Not Design
Requirements gathering is not the process of finding out what customers need, it is the process of understanding the customer. The problem with producing elaborate requirements is not just that requirements change over time or that people change their minds, it is that users can’t tell you what they want because they don’t know. Customers cannot tell you ahead of time what they will actually spend money on. At best, requirements are an approximation of what customers need and a best guess of what will provide them value at the time that they actually use what you implement for them.

Gathering requirements from customers and the market in general is much like removing compiler errors. For any particular module that you are working on, the first error is the most accurate and accuracy goes downhill rapidly from there. After you fix the first error, the results from your compiler or IDE will probably be very different. This is the same with customer requirements. For any particular functional area, the first thing customers ask for is most likely the most accurate. Once they see the new version which incorporates that feedback, what they want next is probably very different than what they would have asked for next before they saw the new version.

The most you can hope for is to gather information and ideas that are useful in producing a successful product. If you just build whatever customers ask for, then you are ceding design to them. Customers cannot design for you. If they can then they are not just customers they are also designers. It may be that in your situation your customer is also a designer, but then you should explicitly think of them that way. Otherwise, you run the risk of making the mistake of blending the process of gathering requirements and creating a design.

When you have multiple customers, it is especially true that the customer cannot tell you what they need. It is rare that you will be able to do everything that all customers asked for, let alone everything that any one customer asked for and thus you will have to predict which combination of requests that your customers asked for will produce the best result.

Specification is Design
When you write a Marketing Requirements Document, Product Requirements Document, Specification Document, or whatever combination of documents you create along these lines and whatever you call them, let's call that "specification." A specification is a design. It is a design because you are taking all of the feedback from the customer and saying, at a high level, "this is what will provide value to the customer." You are deciding and predicting that this specification rather than any other specification is the way to go forward. It is the same as deciding that this line of code vs that line of code is the right way to go.

Specification is the First Approximation
When working with software, even if you have clear requirements/specifications that you have validated with users, it is not always clear how you will implement them.The specification is an approximation in two ways. First, it is only an approximation of what users actually want. Second, it is only an approximation of the final result. This same statement holds true at every stage of the game, from specification to design, to plans, to estimates, to the code itself. From initial customer interaction to final implementation you are building approximation on top of approximation.

I'm not advocating against specification, estimation, or design. It is useful and even necessary to produce these, and you will often hit on solutions or eliminate problems much more quickly and much more economically than jumping right to implementation, but in the end they are still only an approximation of reality, an interlocking web of educated guesses.

Not until you actually attempt to create something real will you find out how close to reality all of these approximations are and the real costs and difficulties involved. The longer you take to turn these approximations into reality, the more likely it is that they will be inaccurate and the larger those inaccuracies will be.

Estimation is Design
Estimation, which is also another word for approximation, is part of design. If somebody gives you a requirement do you just shout out a random number as the estimate? The accuracy of your estimate depends on the amount of design that you put into it. You may not think of estimation as design, but it is. Let’s say that somebody says “I need a module which will calculate the sum of an array.” If you have such a module at hand, you will give an estimate that involves integrating the existing module into the overall product. Deciding to use that module is a design decision. If you don’t have such a module at hand, you will give an answer based on your prior experience doing the exact same thing. The decision to use an approach similar to a past experience is also a design decision. It is part of creating the final design.

On the other hand, if you are given a more complicated requirement, then you will probably break it down into sub-tasks and estimate those. That forces you to think about what it will really take to implement the requirement. The process of deciding what the subtasks are is actually design. The more design you do, the more accurate you can be. The accuracy of an estimation is on a spectrum from “wild guess” to delivery of product, from complete prediction to statement of fact, from “I believe it will take 10 days” to “it took 103 hours.” The other aspect here is how much is research/design and how much is counting. When well-known tasks are what is at hand, then it is a matter of counting. If you know you need to change 20 dialogs and each change will take 10 minutes then you know the task will take 200 minutes. That’s simple counting. If you need to produce something that has never been done before, then it is a research project and you won’t have accuracy until you have removed all of the uncertainty.

Planning is Design
The specific set of features that go into a product is in fact a design. By selecting that set, you are deciding (predicting) that this is the optimal set of features to achieve a chosen goal. While it is true that you may just be choosing a set of work items that sum up to the available time for a release, that is still design, but perhaps not the optimal design.

Design is Design
Obviously, the activities that we associate with “the design process” are part of product design. The design that you have prior to implementation may be a fully fleshed out design document with lots of illustrative figures, it may be in the form of UML, or it might be entirely in your head. As with requirements and estimation, the design is also an approximation. The design that you do prior to implementation is only an approximation because during implementation you have still more design to do and you will discover information that you didn’t have during your initial design.

Implementation is Design
During implementation you are doing two kinds of design: micro-design and re-design. Micro-design is all of the little decisions you make while coding. Will you use a vector or a doubly-linked list? Will you specify an index or let the RDBMS do it for you on the fly? Re-design happens when you find out that once it came time to implement something, an unexpected problem arose. For instance, the design specifies the use of a particular third-party library, but in reality that library doesn’t provide the functionality that it claimed to provide. Another example is that the implementation works fine, but doesn’t provide the expected performance and no amount of tweaking seems to be doing the trick.

Final Validation of the Design
Finally, when you deliver new features to customers, you discover how close your approximations were. You discover what customers like and don’t like, what they use and what they don’t use, what they will pay for and what they will not pay for, what provides value and what does not provide value. This information can then be used to determine what you will put more effort into and what you will discontinue. The tighter you can make the loop from discovery to delivery, the faster you can produce the product that your customers really value.


Next: Software Development is a Search Algorithm

Saturday, September 12, 2009

Transitioning From Scrum to Kanban, Part 1 of 3

Bumping Into Scrum’s Boundaries
Scrum is the most popular Agile process in use today. But if you have been doing Scrum for a while, you know (or will soon experience) that it has some structural problems. Many of Scrum’s activities are tightly coupled to the cadence of the iterations but have a natural tendency towards their own cadences. In order for a story to be done-done-done, all of the work to make sure that it is done-done-done must be done within the iteration. A prerequisite of doing that work is that the code must be complete. That causes problems.

At the beginning of an iteration, there are no stories for testers to be testing until the developers get the first stories finished. At the end of an iteration, while the story validation work is being done on the last stories, the developers (and some of the testers) have nothing to do. A common response to this is that “there is always something to do.” Obviously there is always something to do, but that’s not the point. A key point of Agile is to focus on the highest value work. By definition, the highest value work is whatever is next in the backlog and not anything else. So, if you are doing something other than work required to move that iteration’s stories from todo to done you are working on the wrong things. One approach is to have the developers start on the next items in the backlog, but now you are moving outside the framework of Scrum.

Another problem is that the last stories rarely all transition neatly to done right at the end of the iteration. You may have some stories in progress at the end of the iteration which were hoped to be finished by the end of the iteration. For these folks, there is pressure to fit the work into the time remaining. Other folks may finish up early and not have any stories left to work on. While it is true that the team should be working and thinking as a team and helping each other out, it isn’t always possible to have two people work on the same story.

Just What the Doctor Ordered
There’s a commonly prescribed remedy for all of this: change the iteration length. Sometimes the recommendation is to make it longer, sometimes the recommendation is to make it shorter. In my experience, neither of these recommendations works very well. The reason is that the size of the stories that you work on tends to vary over time. The smaller, the better of course, but some stories are just naturally larger than others. No matter what you do with the iteration length, all you are really doing is changing the size of the problem, you aren’t really removing it.

The Source of the Friction
There are two simple reasons for this friction. It isn’t any easier to predict the future using Scrum. Software development is a creative endeavor. It is unpredictable. There is no way to get stories to all end smoothly at the end of the iteration, regardless of the iteration length or how often it is varied. The structure of the work itself just makes it worse.

Within each story there are two kinds of work: work that is mostly done during the first half of the story and work that is mostly done at the end of the story. The end work depends on the beginning work. As a result, it is impossible to “get the air out of the pipes.” It will always be there. This is illustrated in the following diagram.


The diagram shows two iterations of work split into three "swim lanes." I've artificially put one developer and one QA person into each swim lane to simplify the explanation. The numbers in each swim lane correspond to individual stories, the green areas represent developers and the yellow areas represent testers. The structure of the work means that there will always be areas that are either empty or filled with “other work.” You may have heard that it is good to have slack time, and I agree. However, I believe it is better for slack time to be under the control of the people in the system, not as the unpredictable result of a side-effect inherent in the process.

Long Live Scrum!
So where am I headed with this? Am I anti-Scrum? Am I about to describe a way to fix these problems with Scrum? Neither. I don’t believe these problems can be solved within Scrum. I do think that Scrum can be improved, see “Applying the Decoupling Principle to Scrum,” but I see the real solution as transitioning to Kanban. However, I also believe that it is better to do Scrum for a year or two first in order to build up the discipline of doing One Piece Flow that is necessary for succeeding with Kanban.

Next: One Piece Flow -- Transitioning from Scrum to Kanban Part II

Monday, August 31, 2009

Applying the Decoupling Principle to Scrum

While working on a post about Kanban, I realized that there is a general software engineering principle at work in Kanban that can be applied to Scrum without needing to mention Kanban at all. The principle is: decoupling. That is, separating two or more things which are currently coupled together but don't need to be.

In Scrum, there are many activities which are often tightly coupled to the iteration cadence: iteration planning, having a shippable increment of work, the size of the largest story, iteration reviews, retrospectives, and releases. If you have been practicing Scrum for a while, it is likely that you have already started to decouple some activities from the iterations.

Decoupling Iteration Meetings and Story Point Estimation
Many Scrum teams have a weekly meeting to estimate story points for stories that have made it near the top of the backlog and don't yet have story point estimates. This decouples story point estimation from both the iterations and the iteration planning meeting itself. How far down into the backlog you go depends on what goal you are trying to achieve. If you just want to simplify iteration planning, you only need enough stories to cover one iteration worth of stories and perhaps a bit more just in case some stories aren't chosen for that iteration.

Decoupling Retrospectives
Let's see how decoupling might be applied to more practices. When just starting with Agile, it is much harder to use 1 week iterations than 4 week iterations. If you are doing 4 week iterations, you would naturally do a retrospective once every four weeks. If you move to 2 week iterations, you would naturally do a retrospective every two weeks.

But why not do retrospectives every week or at least every two weeks, regardless of whether you are doing 4 week iterations or two week iterations? Shouldn't the cadence of retrospectives match the cadence of their usefulness? In my experience, there is always something worth talking about every week of any project. There is always something to reflect on and improve. In any case, instead of just scheduling a retrospective at the same cadence as your iterations, schedule the retrospectives at a cadence that makes sense for your needs.

Decoupling Iteration Reviews
Another practice to consider decoupling from your iteration cadence is iteration reviews. Let's say you have 1 week iteration reviews, but it is logistically difficult to schedule iteration reviews involving multiple customers more often than once per month. Perhaps you normally have both internal and external stakeholders at the reviews. One solution would be to continue to have weekly reviews with just the internal stakeholders that are interested in being there every week, and have monthly reviews for external stakeholders. That may actually require a bit more work on your part, but if the value is there, why not consider it?

Simplification and Delegation
Another benefit of decoupling is that by breaking things apart it makes it simpler to tackle or delegate process improvement efforts because you can concentrate on smaller parts which are running at their own cadence. In the example of the iteration reviews, by separating out the external stakeholder meeting, you can now focus on ways to simplify or delegate that part of the process. Perhaps the only problem is getting a web meeting solution in place. Now you can solve that problem without impacting the internal stakeholders.

Consider how the decoupling principle will work for you. I would be interested to hear what you've already decoupled and your thoughts on applying the decoupling principle to Scrum. If you want to read about how to take decoupling to the next level, click on the next post below.


Next: Transitioning from Scrum to Kanban

Sunday, July 12, 2009

Traditional Development == The Game of Telephone?

In theory, traditional development is a good idea. The work of development is broken up into stages in order to reduce risk and increase efficiency. But in reality a significant proportion of projects are shelved, cancelled, or delivered with low quality. In part, traditional develelopment has problems for the same reasons that it is fun to play the game of telephone.

I remember fondly playing a game called telephone in elementary school. In the game of telephone, a message is whispered from person to person. The fun part is that the last person says what he heard to the whole group and everybody gets a laugh out of how a phrase such as "Send reinforcements, we're going to advance" gets inadvertently translated into "Send three and fourpence, we're going to a dance". This is very similar to what happens in traditional software development projects.


Figure: The Traditional Development Telephone Game

The figure above represents a typical traditional development process and some typical times between handoffs. At each stage, instead of whispering the information along, the participants create and use a series of documents, each of which serves a different purpose. As the information moves from stage to stage it needs to be translated into an appropriate form for each stage of development. The documentation also serves as a record of information that was discovered along the way and the decisions and justification for decisions that were made along the way.

The product manager talks to customers and those conversations are translated into Marketing Requirements Documents (MRDs) which are translated into engineering requirements which are translated into specifications which are translated into designs which are eventually translated into code. The end result is then given to the user who often says something pithy like "that's not what I wanted."




At each stage of development there is a risk that the intent from the previous stage is mistranslated. Another way to think of the mistranslation is data corruption. The larger the amount of work that is flowing from stage to stage, and the longer it takes for work to pass from stage to stage, the more likely it is for information to become "corrupted" and the greater the extent of the corruption. Of course, people don't just blindly translate information without interacting with people from earlier stages, they ask for clarification when they think they need it.

When clarification is needed, such as when somebody is writing a test and has a question about how a feature is supposed to work, it requires a conversation with the author of the documention. There is no guarantee that the author is available when needed, knows the answer themselves, or can find the answer in the supporting documentation that they themselves used. That then requires another conversation with the architect, and then the architect with the product manager and then the product manager with customers. The customers may have given their feedback based on ideas they had during the discussion with the product manager but have long since forgotten. The further back in the chain you go, the harder it will be for people to remember the details required to answer clarifying questions.

People aren't very good at remembering the exact details of the work that they did weeks or months in the past. That’s one of the main reasons for creating the documents in the first place. When people are routinely put in the position of having to do something they are not good at, it leads to stress, lower morale, and mistakes. [See "Guilty Confessions of a Software Developer"]

Ok, so now we have a good idea of how customer intent can get lost in translation and how the people developing the software can get stressed out. While that's all very interesting, it isn't very useful unless we can figure out how to act on this information.

Next: Leveraging Human Strengths in the Development Process


Monday, July 6, 2009

Agile Exposes Scaling Problems

One of the first questions that seems to come up in any discussion of Agile is "How Well Does Agile Scale?" Sometimes this is asked explicitly, but more often there is an underlying assumption that Agile does not or can not scale very well. When I was first exposed to Agile, my first impression was that Agile didn’t scale beyond a small team, say 1-12 people.

I used to try to tackle the question head on, but then I realized that there's something else going on here. Let’s take a step back. What do we currently assume about traditional development? I think we come to the discussion thinking that just because there are teams of 100 engineers, 500 engineers, and even 2,000 engineers doing traditional development, that traditional development is a proven quantity when it comes to scaling. Let’s first ask the question: “How well does traditional development scale?”

To answer that question we first have to define "scaling." I think a good working definition is that as you add new resources, there is a linear increase in effective output with little or no decrease in efficiency. For software, output and efficiency translate to new functionality and productivity. That would mean that if you have a 50 person engineering team and you add 50 more people you get twice the output. But when was the last time you saw that? Have you ever seen it? In my experience, after talking to hundreds of development organizations doing traditional development, productivity falls and thus output does not increase linearly with additional resources. In many cases, output actually decreases as more resources are added.

What do you actually do to "scale" your development organization? Do you have meticulously updated Gannt charts and estimates? Do you schedule lots of meetings? Do you spend a lot of time making sure that requirements and designs are just right? Do you reserve 30% of the development schedule for testing (and fixing)?

In my experience, after talking to hundreds of development organizations, the answer to the question “How well does traditional development scale” is “not very well.” We've just suffered along with this problem, in large part because while the pain was there, the root causes were difficult to trace, let alone address.

The main point here is that if you are in the process of rolling out Agile to a large organization, don't be discouraged when you run into scaling problems. The problems were always there, they just weren't as obvious. Now, instead of wondering why things aren't coming together as expected at the end of the project, you may find out right away that your organization doesn't really have a good way to coordinate API changes for APIs that are used by multiple teams. As Agile exposes problems like this, you can take steps to solve the problems and thus create a more scaleable development organization that just happens to be doing Agile development.

Tuesday, February 10, 2009

Poll - Short Iterations, The Benefits

Short iterations are the practice of breaking up a release into 1-4 week development cycles that each produce a shippable increment of work. Some of the benefits of short iterations include working software that you can show to people in order to get their feedback and having nothing in progress at the end of the iteration so you can change your plans to take into account market changes, feedback from customers, or information you discovered while implementing that iteration. Also, all of the tests for the functionality implemented during the iteration have been written and run and you have a well known starting point for the next iteration.

There are some assumptions hiding in this practice. It assumes that you believe that incremental design is possible and that you believe that any refactoring you have to do in subsequent iterations is worth the benefits as described above.

So, if you were starting a company with your own hard-earned cash, would you use short iterations or wouldn't you?



Next: Poll - Whole Teams, The Benefits

Poll - Product Backlog, The Benefits

A product backlog is a list of high-level product requirements (or user stories), prioritized by business value (typically determined by a product manager or product owner). It contains entries for any and all work that is performed, including bug fixes. As new requirements are gathered or submitted, they are inserted into the backlog at the position that best represents their business value with respect to requirements that have already been entered. As requirements are met, they are removed from the product backlog.

A backlog gives a clear context to discussions of priority. Anybody can go and look at the backlog to see the position of something they have a stake in. If it is lower than they think it should be, they can examine the backlog to see what is higher in order to help frame a discussion around either moving it higher or moving other things lower.

So, if you were starting a software company with your own hard-earned cash, would you use a product backlog or wouldn't you?



Next: Poll - Your Preferred Methodology

Tuesday, January 20, 2009

Getting Management and Engineers Out of Each Other's Hair

This is the fifth in a series of posts on self-management that began with "The Use of Self-Managing Teams Outside the Context of Software Development."

Short Iterations Increase Management Leverage
One of the hardest jobs of a manager is discovering and resolving problems. If you don’t know about a problem, you can’t resolve it. If you discover a problem late, you can’t do much about the negative effects it has already had. If you don’t get feedback on the results of the actions you take for a long time, it is difficult if not impossible to judge the effectiveness of your actions. Short iterations, the practice of breaking up a release into 1-4 week development cycles that each produce a shippable increment of work, vastly increase the amount of feedback available to management for making good decisions. It also provides more opportunities to make adjustments and judge their effectiveness.

Burndown Charts are a Management Dashboard That Everybody Loves
A burndown chart is a useful tool for measuring the amount of progress, positive or negative, during an iteration which clearly illustrates trends which may indicate problems. It is simply a day-by-day chart of how much effort remains. At the beginning of an iteration, 100% of the work for that iteration remains. At the end of the iteration, there should be 0% remaining.

An important multiplier of the effectiveness of a burndown chart is its visibility. A clearly visible burndown chart makes it obvious to everybody how the project is progressing. Nobody wants to see a burndown chart that isn’t making progress, and nobody wants other people to see lack of progress for a significant period of time. The burndown chart helps to motivate and inspire. If your own work is going well, but the chart isn’t going down in general, you’ll be more engaged in helping to solve problems that the team is having overall. When used effectively, the burndown chart reduces the effort required for a manager to determine that there is a problem and also reduces the need for the manager to cajole the team into taking corrective action.

Retrospectives Emphasize That You Are All In This Together
A retrospective provides a forum for the team to talk on a regular basis about what worked and what didn’t work as a team, to discuss ideas for improvement and to work out problems. Instead of a manager having to unearth all problems and come up with all solutions, a retrospective accomplishes much of this, providing the manager with more bandwidth to deal with sensitive issues and to focus on people management. Retrospectives are particularly effective when combined with short iterations because problems have less time to fester and there are more opportunities to take corrective action.

User Stories Reduce Micro-Management
Agile prefers user stories over requirements. User stories are simply stories that describe what is needed from the user’s perspective. User stories help to separate business value from implementation and focus all parties on the desired outcome. The separation removes the invisible constraints which can appear when the engineer assigned to a task is given a specification which completely constrains the problem such that only one solution is available. By focusing on the outcome desired by the user, the engineer working on the task has more freedom to utilize their creativity and ability to innovate without the risk of implementing something that the user doesn’t want.

There are two reasons that user stories support self-managing teams. First, they reduce the temptation of technically minded managers from becoming an implementation bottleneck. Second, they encourage team members to innovate and take on more responsibility which increases their self-sufficiency. This is much easier to do within an Agile environment because there are more practices in place such as short iterations, burndown charts, and retrospectives which encourage learning while reducing the risk of making mistakes.

I hope you have enjoyed this series on how Agile practices reduce and redistribute the job of management and thereby increase your capacity for self-management. If you missed the beginning, the first posting is "The Use of Self-Management Outside the Context of Software Development" .

You may also enjoy reading the the online mini-version of the book that I am working on called "Zero to Agile in 90 Days or Less."

Monday, January 19, 2009

No-Brainer Self-Management Practices in Agile Part 2


Whole Teams Improve Coordination and Communication
A whole team is a small group of people (no more than 12) that work together towards a common purpose, primarily spend their time as part of the team, and as a team have all of the skills they need in order to be self-sufficient. These skill sets may include server side programmer, web designer, tester, technical writer, scrum master, product owner, etc. The whole team practice contributes to self-management by reducing the amount of coordination required in order to achieve a goal. For instance, instead of having to coordinate with a QA group in order to find somebody that can test a piece of software, having a QA person as part of the team means that there is always somebody familiar with the software available to test it.

Another benefit of having a whole team is that it makes it more obvious if you have resource imbalances. If the QA folks in the team can’t keep up with the developers, then you either have too many developers on the team or too few QA folks. If your front end developers can’t keep up with the folks working on the back end, then you have a resource imbalance. You either need to add more folks with the right skill set, or you need to reduce the amount of work being done on the back end.

When you have a whole team, you spend less time waiting for other groups and bringing part-time participants up to speed, you lose less time due to communication delays, and individuals spend less time multi-tasking between multiple projects. Taken together, the benefits of whole teams can have a significant impact on reducing management complexity which makes it easy for teams to do more self-management.

Collocation Further Improves Coordination and Communication
Collocation is closely related to whole teams. Collocation is simply having everybody in close proximity to each other. This compounds the coordination benefit of whole teams.

If you have a large group of people that are not all near each other but they are all working towards a single deliverable, collocation may seem impractical on the surface. However, collocation at the whole team level is more important than collocation of multiple teams. Focus on creating whole teams that can collocate rather than collocating the whole group of people.

The challenge with both whole teams and collocation is that they often require either relocating people, changes to management structures, or both. However, the benefits of having a tightly coordinated team working towards a common goal far outweighs the difficulties associated with creating collocated whole teams.

Friday, January 16, 2009

“No-Brainer” Self-Management Practices in Agile

While there may be some confusion over the meaning of self-management in Agile, not to mention some contention as to whether or not it is a good idea, many of the Agile practices contribute to self-management without requiring the wholesale adoption of self-management. For simplicity, I will define “self-management” as anything that is done by a team member that would traditionally be done by a manager. The practices contribute to self-management either by reducing the amount of management required or by encouraging the delegation of management tasks to team members. Some practices do both. As a result, managers have more bandwidth for dealing with things which are a more leveraged use of their time.

The Agile practices related to self-management include:
  • whole teams
  • collocation
  • short iterations
  • using a scrum master
  • using a product owner
  • user stories
  • maintaining a product backlog
  • assignment of tasks by team members
  • estimation of tasks by team members
  • producing a burn down chart
  • retrospectives
Simplifying and Redistributing the Management Load
Let’s start with a simple example: task assignment. Traditionally, tasks are assigned to engineers by their manager. In Agile, tasks are selected by the engineers themselves. It may take some time for everybody to get used to this and to work out the kinks, but the practice itself is not particularly earth-shattering.

Certainly, somebody may find themselves struggling with a task they don’t fully understand, or one engineer may accomplish a task more slowly than whoever the manager might have chosen to do the task. But is that really all that different than what typically happens when the work is assigned by a manager? How likely is it that a manager has enough time to devote to the minutia required to optimize task assignment? Wouldn’t it be better for the manager to spend their time mentoring team members on how to pick tasks that are appropriate for them while at the same time encouraging engineers to stretch their capabilities?

Wednesday, June 11, 2008

Sustainable Pace: Supply vs Demand

In a traditional project, the demand for resources from the four major aspects of software development see-saws dramatically over the course of a project. These aspects are project management and planning, architecture and design, development, and QA. You need resources on hand to serve the peak demand level, but during periods of low demand those resources will either be idle or used for activities which have a lower ROI.

A common circumstance is that there are insufficient resources on hand for the peak demand level and so people end up working in “crunch mode.” During crunch time, people tend to make more mistakes. Agile levels demand out over time and removes this see-saw effect which simplifies resource planning and removes the need for crunch time.


In the figure above, the straight green lines represent the resource load in an Agile project and the zig-zagging purple lines represent the resource load in a traditional project.

With traditional development, delays during development compress most of the testing to the end of the process which then requires taking shortcuts due to schedule pressure. I used to think that one way of compensating for insufficient QA resources was to delay the release until QA finishes. On the surface it seems to make sense. But only if the folks writing code sit on their hands while QA does their work. Ok, so you have multiple projects and the developers work on another project. But then they finish that. Now QA starts on the second project and the developers move to the third. The problem is still there.

On the other hand, as a result of the need for increased QA resources during testing, you may have two other problems. If you have enough QA resources to handle the pressure of the endgame, you may have too many QA resources during the rest of your development cycle. Alternatively, you may bring on additional QA resources on a short-term basis to compensate. Both of these options are obviously undesirable.

There’s a natural balance between the amount of effort required for developing something and the amount of effort required to QA it. No matter what you do, if you have the wrong ratio of development resources to QA resources, it will cause problems. If development creates more than QA can absorb, you will create a backlog of QA work that will always grow.

There are six options for dealing with a QA backlog: do less QA than needed and thus shift the burden of finding problems that you could have found onto your customers, increase your QA capacity, decrease your development capacity, have development idle, have development help with QA or allow the backlog to grow. The larger your testing backlog, the longer it will take to ship it and the greater your opportunity cost.

The imbalance may be in either direction. After you transition to Agile development, you may find that you have more QA resources than are needed. In that case, you have the option of having QA take on some of the work currently done by developers. See The Role of QA in an Agile Project for more on that topic.

This natural balance holds between all four aspects of software development. Depending on your organization, there may be an imbalance between supply and demand at any stage in the pipeline. Wherever there is an imbalance you have the same six options as described above. For example, you may end up with project plans that are never used, developers idle because the design isn’t ready yet, etc. To the extent that some of the resources are actually the same people you can use that fact to manage this problem.

When using short iterations, resource imbalances are easier to detect and correct. Having balanced resources means that all development activities are done consistently and on a regular basis and there is no need to take the shortcuts that are typical of traditional development.